In recent days, we have replaced a bar screen competitor in a lifting position.
The main difficulty of this installation is the depth of the canal, which is only 6 meters. But also the fact that it bar screen is installed in a closed space.
Between the disassembly of the existing equipment and the assembly of the new one bar screen, the intervention of our technicians took a whole day.
Technical data
Provision of a bar screen automatic
- Type XG12
- ALL INOX 304L
- Max flow rate 400m3/h
- Interference 30mm
- Depth under laying plan 5900mm
- Channel width 800mm
- Chassis made in 3 parts
Options selected
- On-site transportation
- Demolition of the bar screen existing structure
- Assembly of the new unit bar screen by 2 technicians FB Procédés