Opens in a new tab

2 new equipped motorway service areas

21/12/2022

In recent days, two motorway areas in the south of France, located in the same commune, have each been equipped with a set consisting of a vertical bar screen press and a compaction screw.

The electric boxes are attached to the side of the bar screens unit, allowing for easy operation and adjustment of the entire system.

In the event of a problem on the pumps bar screens, they are equipped with a bypass system that allows the wastewater to flow into a parallel channel equipped with a manual screen.

Finally, the installed equipment is protected against freezing and can therefore operate despite difficult weather conditions.

In the event of similar projects, do not hesitate to contact our sales team, who will be able to best assist you in developing your needs.

Technical data


Supply of 2 bar screens automatic machines

  • Bar Screen SG400
  • ALL INOX 304L
  • Maximum flow to be treated 1m3/h
  • Interference 15mm
  • Depth under laying plan 1500mm
  • Associated with 2 compaction screws Type VCP150

Options selected

  • Standard FB electric kit Processes
  • Automatic tightening on each compaction screw
  • Unlocking the Bar Screens locking screws of the compacting vise
  • On-site transportation

Photos of the project


Bar Screen on a motorway area
Bar Screen with a screw on a motorway area